Aired Oct 23, 2026 · 20 min
Listen on: YouTube · Spotify · Apple Podcasts
The data center boom is creating enormous opportunities for utilities, but what happens when the grid can't keep up?
In this episode, Chris Sturgill, Partner at ScottMadden, talks about the financial and operational risks behind soaring data center electricity demand.
They explore why data centers can be built in just 18–26 months while grid infrastructure can take 5–10 years, whether data centers could actually lower electricity bills, and how utilities can distinguish serious development projects from speculation. Sturgill also explains why promises of flexible data center electricity consumption remain largely unproven and what utility leaders should do to avoid costly infrastructure mistakes.
Thank you to our partners at ScottMadden for making this episode happen. To learn more about ScottMadden visit: https://www.energycentral.com/ScottMadden
Watch the full episode
Get the stories behind the conversation. The Energy Central daily newsletter covers what electric utility leaders need to know, every weekday morning.
Full transcript
Chris Sturgill: It's really hard to make predictions, especially about the future.
Matt Chester: It might take 18 to 26 months to build, but new grid infrastructure, we're looking at five to ten years these days.
Chris Sturgill: A couple of months ago, we saw PJM drop 3.8 gigawatts of load. But a dose of realism when it comes to the physics of building infrastructure always helps.
Matt Chester: Can data centers lower your power bill? Can they really flex when the grid is stressed? Can utilities develop the grid infrastructure needed for tech that's built in 18 months? Everyone has a pitch, but few have the actual playbook. Today, we're joined by Chris Sturgill, grid modernization and clean energy partner at ScottMadden. And together, we pressure test the hype and give utility leaders the insights that they can actually use. And we want to give a shout out to ScottMadden for sponsoring this episode. We'll talk more about them as this conversation goes on.
So Chris, utilities are getting flooded with huge data center load requests right now. Your data center playbook report mentions developers may show up before they have land, permits, financing, or even an end user. So in this environment, how do you separate serious projects from those that are just pure speculation?
Chris Sturgill: Thanks, Matt, and you're right. Utilities are beset by all these applications. And in almost no time, the paradigm really flipped. So it went from utilities looking to go out and attract new load, because that's a way to show growth, to now being beset by too many applications to even review. And what utilities are doing to help with this is setting up structured intake processes to vet these projects, both from a commercial perspective and from an operational feasibility perspective.
So in terms of what looks like a good project from a commercial perspective, those that are serious would have an identified project sponsor with a track record of performance, a financing plan with upfront deposits, and a willingness to commit financial resources as the project progresses. And then looking at it from the technical side, those projects that have demonstrated site control, siting with proximity to existing resources, credible load estimates with options for phasing or ramping in power, a schedule with realistic timelines around things like siting, permitting, design, procurement, and all of that, and other infrastructure coordination when they're looking for water or fiber connections.
Matt Chester: Excellent. Yeah. And so if you're seeing from a developer all those things, you know, obviously there's always the question of, you know, how much background is being put into it, how much they can come into fruition. I'm curious from your experience, are there almost under-the-radar red flags, or on the other side, green lights that planners can watch for across the lifecycle to really, you know, get under the hood about whether these things are coming or not?
Chris Sturgill: Yeah, I think the red flags would be those things that are kind of flying in the face of those commercially or technically serious projects. So it's kind of urgency without clarity around the schedule, or it's opaqueness or lack of visibility into kind of who the project is, where it will be sited, and that they demonstrated site control and all of those things. So it's, so it's a bit of a diligence exercise in making sure that the developers have dotted their I's and crossed their T's.
Matt Chester: So for the utilities involved here, there's obviously a lot at stake. And I'm curious if you can talk about what are some of the biggest operational risks, financial risks that they're taking on.
Chris Sturgill: Yeah, thanks, Matt. And they are taking on both those risks. So on the financial side, it's the Goldilocks question of managing overbuild versus underbuild and missing the opportunity for growth. On the overbuild side, you're looking at things like stranded asset risk. And thus far, that hasn't really borne out because the markets have been so short of power. But at some point, if everyone keeps building, there may be a tipping point where there's an oversupply. And if you have counted on off-takers of that, you may end up being long power when you didn't mean to be.
There's also counterparty risk on the financial side, which is that we're seeing a lot of long-term contracts being set up, but if that entity isn't around, you can't sue nobody. So there's counterparty risk to manage as well, and that's why that commercial vetting that we talked about on the project intake becomes so key. And then there's also potential for cash flow crunches where utilities are having to commit to infrastructure projects up front. They get built and then you start collecting revenue from the customer once operational. And that can be years in the making. So we're seeing a lot of deposits and CIAC and things like that that would help with the cash flow management.
Matt Chester: Yeah. Are there any real-world cautionary tales that you can share with us where you've seen things go sideways, whether or not you can actually name who is involved?
Chris Sturgill: Not really on the financial side, but you mentioned operational risk as well. And I think that's where you've seen a lot in the press around data center trips offline. And then all of a sudden you're seeing gigawatt-scale drops in load and over-frequency, over-voltage too, as a result, in utilities, and ISOs, RTOs and NERC are looking at standards to address that. I think a couple months ago, we saw PJM drop 3.8 gigawatts of load, and that's got a lot of people's attention.
Matt Chester: You mentioned sort of the Goldilocks situation where key to all of this is reliably and accurately, as much as possible, predicting future demand. And for the utility leaders, the cost of forecasting wrong can be astronomical. So how do the leaders of the utilities balance that need for accurate forecasts with the inherent uncertainty that comes with them?
Chris Sturgill: Yeah, I really sympathize with utility forecasters because for years their job was what it was last year, plus one or 2%, and it was pretty stable. And now it's kind of like the Yogi Berra quote of, it's really hard to make predictions, especially about the future. Because forecasting is at that front of the planning process, sharpening that process is top of mind. It goes back to that Goldilocks dilemma we were just talking about, and you're either overbuilding with unused infrastructure or you're underbuilding and then running into resource adequacy issues.
And so there are a handful of kind of tactical steps that we've seen people taking to help with this. The first is around establishing stage-gated forecast categories that apply to the portfolio. So if a project is kind of just at the outset, has just been taken in, it really doesn't factor into the load forecast in the same way that a more mature project that is under construction would. And so you're almost qualifying the contribution to the forecast as projects mature. We're seeing more granular and more frequent forecasting. So if it was an annual cycle, it might now be quarterly. And maintaining a consistent source of record or source of truth for the data around these projects so that forecasters and planners and the finance folks and the customer development groups are all kind of singing from the same sheet of music there. And then finally, it gets into a feedback loop of making sure that if we have assumed certain load shapes or certain phasing of consumption, that that matches what developers are doing in practice.
Matt Chester: One of the reasons that we're seeing data centers and energy really capture a lot of headlines is the intense focus on rates by everybody these days, in the political sphere and at the utilities, customers themselves. And at least within the data center sphere, there's a popular narrative that building these data centers can lower power bills by spreading fixed costs over huge sales. But in your report, you say that high load factor usage alone does not mean a project will necessarily lower rates. So if that's the case, what actually determines if regular ratepayers benefit or get burned from these data centers being built in their backyard?
Chris Sturgill: It's a subject of much debate and really a way that you see the headlines impacting dinnertime conversations that you didn't really expect, where folks know that I work in the energy industry, so I get a lot of inbound questions about data centers and costs because that's the natural connection to draw. I think the correlation is there, where data centers are a relatively new topic of conversation in the last five years and energy costs have gone up in the last five years. So kind of, thus it must be so.
And I think if you can take it on the simplest ends of this, which is if there was a big data center project coming on that was able to use kind of all existing available capacity, so no incremental costs, it would in fact spread the same fixed costs over more megawatt hours and put downward pressure on rates for ratepayers. But I think that capacity has been consumed. So now we're in the era of incremental infrastructure to support incremental demand. And the factors that go into that are kind of the headroom, the way the tariff is structured, the consumption pattern of the data center, and the phasing of how that load comes online.
And that's where utility cost of service studies come in, and the need to set up the tariffs in a way that cover all those costs that are directly attributable to the data center and then whatever they are consuming of incremental capacity. And we've seen some interesting data center tariffs come out of Evergy and AEP that try to assign those incremental values and get that math right. I don't know that we will see the math play out on that in a definitive way for several more years, because we're going to have a lot of data. New assets come on, are getting built, they're hitting the CapEx budgets, and will go into future rates. So it's almost too early to tell, but that's the balancing act on the math and where utilities are spending a lot of time, on cost of service studies and tariff design.
Matt Chester: And you mentioned, you know, too early to tell, but at the same time, all sorts of stakeholders are looking to build in protections now for consumers, whether that's politicians, consumer advocacy groups, regulators themselves. And we're seeing a lot of everything from voluntary pledges to mandates being debated, bans coming into certain localities. I'm curious what concrete protections you think that those consumer advocates should demand upfront to actually ensure that those benefits come to be.
Chris Sturgill: Yeah, it gets back into that tariff design. So you want provisions that deal with delayed projects or canceled projects, or where consumption doesn't match what was stated, and so you've overbuilt infrastructure for this project that's now getting spread elsewhere, and early termination, early exit. So you want to have protections against all of those. The cost of service piece of it wants to look at both the incremental, almost directly ascribed costs, but also what portion of existing capacity are these projects consuming that they should pay for, that they should, they're the causer of those costs. So those, and then transparency and reporting and tracking. So, you know, project said this, that was seven years ago, where are we now? And understanding if the benefits have borne out, or if, I think, as you said, the ratepayers have been burned.
Matt Chester: And one of the other sources of consistent tension in this space is timeline. Data center, it might take 18 to 26 months to build, but new grid infrastructure, we're looking at 5 to 10 years these days. So how do utilities look to close that timeline gap when it's so wide?
Chris Sturgill: It is a wide gap, and it's probably not one they'll ever close fully. I think that the answer to when would you like this power demand, or when and how much would you like this power demand, is all of it. And two years ago, you know, if you think about all the steps we've been talking about so far around forecasting and planning and project vetting and contracting, all of that gets you to a point. And then you have to actually go design and procure all the material for and build the infrastructure to serve that. And that's non-trivial.
What we see utilities doing to try to close that gap is looking at things like standardized designs that mitigate challenges with kind of one-offs and a lot of back and forth on the design process between utility and developer; looking at breaking it out, breaking out the work and the capacity delivery in phases so that as they are able to build infrastructure and bring more power to bear, the data center can start ramping up its load; looking at contracting arrangements for long lead time equipment, sometimes pooling, sometimes kind of strategic sourcing agreements; looking at addressing labor shortages, both on the design side and the build side, with EPC relationships; and looking at kind of change control procedures so that as the design matures and if it changes, you can quickly determine whether or not that's going to result in a timeline shift because new equipment's needed or a new component has been added.
So there's lots that go on there. And again, none of that probably brings you to a point of 18 months where it takes it for the data center. But I think that can be, it all helps. And then you're working on the relationship with the customer and helping them know what to expect at every point in the process. So they don't expect magic. They're expecting reasonable build of the project.
Matt Chester: Yeah, that's what I was going to ask. Is part of the onus on the tech companies who are wanting the data centers to have more realistic expectations and maybe meet those utilities halfway?
Chris Sturgill: I think so. They may get creative and decide that that's not working fast enough and they're going to look for kind of microgrids and building it themselves. And they've certainly got the balance sheets to do that. But a dose of realism when it comes to the physics of building infrastructure always helps.
Matt Chester: Yeah, yeah. Physics aren't flexible. The other story we often hear as kind of pushback to the data center criticism, as ways that they can be good stewards of the grid, comes from flexible load. The idea that a data center can shift their compute power time-wise, they can run backup batteries, they can curtail completely if needed when the grid is strained. How much of that is actually real and being used today? And how much of it is maybe what we can call pitch deck optimism?
Chris Sturgill: Here in Raleigh, North Carolina, I'm just down the road from Duke University. They put out a really interesting study on this. And there are potentially gigawatts of kind of available capacity if you can start shifting around load. And I think that's attractive for kind of obvious reasons in terms of avoiding the cost and time of building all of that. But I, so the idea is sound. I think to date it has largely been kind of a paper exercise, and pitch deck optimism, as you might have said. It certainly has drawn interest in groups trying to figure this out, like EPRI's DCFlex and working consortiums.
I think one important thing to keep in mind here is the operational time horizon, which is things like demand response, that utility operators have the purview and the mandate to kind of control things in the moment and call upon demand response resources or curtail loads if they need to. But that's very different than the planning time horizon, where utility planners are saying, I know that this resource will be here as stated in the future. And that's where I think the longest gap is in terms of getting operational flexibility stood up in a meaningful way, is that planners will probably not count on that kind of capacity until there's some performance track record of those resources showing up in that way, that there are some contractual mechanisms to make sure they do, or penalties if they don't. And that gets back to grid stability and grid safety, and probably not something they're going to budge on too readily.
And then the data center side of that is, well, I don't know how often you're going to call it. I don't know for how many hours. I've got a significant opportunity cost when you do, if I've got to disrupt my computational workloads. So I think both parties are pretty wary about that as a real solution. And it'll take some, I think, successful proof of concept to get there.
Matt Chester: Yeah, that makes sense. And you mentioned there's different time horizons, but I imagine there's also some variation in how applicable it is based on geographic region or the local grid mix or even the type of data center.
Chris Sturgill: It could. The type of data center and what kind of loads they are willing to shift or can't because it's a long training run kind of workload, that certainly plays into it. The ramp of your generation mix and how quickly you can ramp that up or slow it down.
Matt Chester: Excellent. So Chris, we want to end the conversation on an actionable point. So if you were in the C-suite, you're steering a utility through this wave over the next five years, what's the one biggest mistake you'd be trying to avoid right now?
Chris Sturgill: I think it's locking into something prematurely. So the biggest thing right now is just these great cones of uncertainty and where things are going to go. And so I'd want to maintain kind of nimbleness in my processes, probably most of all that link between the capital planning and budgeting forecast and the actual operational kind of infrastructure planning processes, and making sure that I'm staying on top of my projects. I'm seeing what materializes and when, and how quickly I'm able to build and respond. And then also, if things start to pull back, not being so far kind of out over the edge on that that you get burned financially.
Matt Chester: It's a lot to juggle, but it sounds like, you know, the map is out there for how to do it.
Chris Sturgill: It's an exciting time. Thank you.
Matt Chester: It is, it is. And it's a critical time. Again, we're talking about this a lot now, but we know it's only going to ramp up. So we thank you for joining us to share your insights in this fast-moving space today.
Chris Sturgill: Great. Thank you, Matt. Pleasure to be here.
Matt Chester: And thanks as well to ScottMadden for sponsoring today's episode. ScottMadden is a management consulting firm serving clients across the energy utility ecosystem. Areas of focus include transmission and distribution, the grid edge, generation, energy markets, rates and regulations, corporate sustainability, and corporate services. And thanks as well to our audience for joining us today on Power Perspectives. We will see you next time.